A Realistic Timeline, and Why Projects Slip

Last updated:

A typical eight-week build

WeeksWhat happens
1Discovery, structure, sitemap agreed
2–3Design of key templates, reviewed
4–6Build, template by template
6–7Content loaded, forms and tracking configured
8Testing, redirects, launch

Content is the delay

In our experience content is the cause of more overruns than every technical issue combined. Sites sit built and empty, waiting for copy that was promised in week three.

Agree who writes what, and when, before the project starts. If copywriting is not in scope, someone in your business needs the time booked.

The other three causes

  1. Feedback — a design review that takes two weeks pushes everything two weeks
  2. Access — hosting, domain and system credentials arriving late
  3. Scope — a booking system mentioned in week five

What we need and when

  • Week 1: brand assets, existing content, access to everything
  • Week 2–3: design feedback within three working days, consolidated
  • Week 5–6: final content, or agreement to launch with placeholders
  • Week 8: launch decision and someone available on the day

Protect the launch date

Two mechanisms work: consolidate feedback into one response rather than a trickle, and put anything new into a phase two list rather than absorbing it.

Both keep the project moving without losing the ideas.

Frequently asked questions

Can it be done faster?

Yes, by narrowing scope — fewer templates, less content, launch and extend. Compressing the same work rarely ends well.

What if our content is not ready?

Launch with the pages that are, and add the rest. A live site with eight good pages beats a finished one that is still not live.

Who should give feedback?

One person collecting everyone's input. Feedback from four people separately, contradicting each other, is the second most common delay.

What happens after launch?

Two to four weeks of small fixes as real use reveals things. That should be included, not extra.

Keep reading

Need a site live by a specific date?

Tell us the date and who is writing the content. That second answer decides whether it is achievable.