Starting an Automation Project: The First Four Weeks

Last updated:

Week one: measure

Before deciding anything, measure what you have. Pick the two or three candidate processes and record, for a week: how many times each happens, how long each takes, and how many go wrong.

This week costs you almost nothing and it settles every argument that follows — which process to choose, whether the project paid for itself, and whether to fund the next one.

Measure by observation and tally, not by asking. Self-reported figures are wrong in both directions.

Week two: choose and specify

  1. Score candidates on frequency, tedium, error cost and how little judgement each needs
  2. Pick one — the one with the most repetition and the least thinking
  3. Write the happy path as numbered steps
  4. Write the exceptions, and keep going until you have at least five
  5. Name the internal owner and confirm they have half a day a week

The exceptions list is the part that determines whether the project succeeds. A specification without one is not finished.

Week three: get comparable quotes

Send the same written scope to three suppliers. Ask each for the price broken into phases, the assumptions they are making, what is explicitly out of scope, and who would do the work.

State your budget range. Withholding it produces proposals scoped for the wrong scale and wastes everyone's time.

Week four: decide

  • Compare on what is being built, not on the headline number
  • Read the assumptions section first — it reveals who has thought about your problem
  • Take one reference from a project of similar size, not the flagship
  • Check ownership of code and accounts is yours, in writing
  • Confirm the maintenance arrangement before signing, not after

What happens next

A well-prepared first phase runs six to twelve weeks: specification, build, parallel running against the manual process, then cutover. Expect to spend half a day a week throughout.

Then re-measure against your week-one baseline. That number is what funds phase two, and it is why week one mattered.

What to avoid in the first project

Anything spanning several departments, anything where the process is still being argued about, and anything that requires a third party to build something for you first.

Save those for when you have one success behind you and an organisation that believes automation works.

Frequently asked questions

What if we cannot spare the internal time?

Then the project is under-resourced on your side and will slip. Half a day a week from a decision-maker is the minimum, and projects without it are the ones that stall.

Should we do a paid discovery instead?

If the process is complex or you are unsure what to scope, yes. A one to three week discovery producing a specification you own is money well spent.

How much should a first project cost?

£5,000–£15,000 for a single well-defined process. If quotes are far above that, the scope is larger than one process.

What if we pick the wrong process?

Scoped small, you lose weeks rather than a year, and you learn something concrete about your own operations. That is a survivable outcome.

Keep reading

Ready to start but not sure where?

Do week one first, whoever you end up using. Then send us the numbers and we will tell you which process to target.

Book a free 30-minute call Get a project estimate WhatsApp us

Related services

What we build for problems like this one

Business AutomationCustom Software Development